You are the Program Manager for the Defense Logistic Agency's new procurement activity. You recently met individually with all of the bidders on a new procurement project. In one of those meetings you accidentally made one of those bidders aware that his company's bid too high. You should? Re-open discussions and advise all offerors of their standing relative to one another with regard to price prior to submission of the final proposal revision Arrange to "run into" the other bidders and imply they should not assume they are giving the lowest price Dump your blunder on the desk of the Contracting Officer Keep the disclosure under your hat

Respuesta :

In the given scenario, one should re-open discussions and advise all offerors of their standing relative to one another with regard to price prior to submission of the final proposal revision. The correct option is a.

What is procurement project?

When it comes to project management, procurement refers to the process of buying, renting, or hiring outside help to complete a task. Like any other process in the project, these linkages require management.

Prior to submitting the final proposal modification in the scenario described, one should reopen conversations and inform each offeror of where they are in relation to one another in terms of pricing.

Thus, the correct option is a.