Answer:
a) 646 truck loads
b) $36, 430
Step-by-step explanation:
Since we need to transport 4520 tons of cement and each mixer can carry 7 tons, the total number of loads = 4520 / 7 =645.71 rounded up to 646 loads (Answer a)
b) The first 30 truck loads will cost $85 per load so total cost = 85 x 30 = $ 2,550
The remaining (646-30) truck loads cost $55 per load so cost for the remaining tuck loads after the first 30 = (646-30) x 55 = 616 x 55 = $33,880
Total cost = 33,880 + 2,550 = $36, 430