You have just discovered an error in the implementation plan that will prevent you from meeting a milestone date. The BEST thing you can do is: Select one: a. Develop options to meet the milestone date. b. Change the milestone date. c. Remove any discussion about dates in the project status report. d. Educate the team about the need to meet milestones.

Respuesta :

The best thing one can do after discovering an error in the implementation plan is to develop an options to meet the milestone date.

What is an implementation plan?

An implementation plan refers to a plan that outlines the steps to take when trying to accomplish a shared goal, objective, preset goals etc.

Thus, the option of develop an options to meet the milestone date will help to ensure the meeting holds

Therefore, the Option A is correct.