As you progress from projects to continuous processes, all of the following statements are true, EXCEPT: Group of answer choices Supplier ties are more formal and of longer duration Degree of worker control over the pace of the process increases Finished goods inventories are larger Long-term sales forecasts become increasingly important for planning purposes

Respuesta :

When we progress from projects to continuous processes, it is not true that Degree of worker control over the pace of the process increases.

What happens when we move to continuous processes?

Because the processes of production in a company are now continuous, it means that workers will be needed to work repeatedly overtime.

This means that workers will have less control over the times they have to work and the pace of production.

In conclusion, option B is correct.