The statement that is not true about master production schedule is "C. The master production schedule is a sales forecast."
The term "master production schedule (MPS) is used to refer to the specific allotted time period for the production of each commodity. This means that each individual commodity is given a specific scheduled time for its production.
- MPS shows the scheduled idea of what product is to be produced and in how much time.
- This schedule allows for the presentation of what specific commodity is to be produced and at what time.
- This schedule is a sort of timetable that regulates and monitors the production of individual commodities. It also provides inputs about the materials required and helps in the planning systems.
- But what it does not do is predict the sales or provide a forecast of sales.
While the Master Production Schedule is used more like a timetable to regulate and identify what item has to be produced and when it also helps in the proper production and keeping tabs on the production schedule. Thus, the statement that is wrong about the MPS is option C.
Learn more about MPS here: