On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.

Respuesta :

Answer:

2021

revenue                 2,666,667

we have cost for  2,000,000  

income for                666,667

2022

revenue                     3.278.400‬

cost                           2,500,000    

income                          778.400‬

2023

revenue          2,054,933‬

cost                3,800,000  

loss                   1,745,067‬

Explanation:

2,000,000/ (2,000,000 + 4,000,000) = 1/3

in 2021 a third of the contract was complete therefore we recognize a third of revenue:

8,000,000 x 1/3 = 2,666,667

we have cost for   2,000,000

income for                666,667

2,500,000 / (2,500,000 + 3,600,000) = 0,4098

we recognize revenues for 40.98 of the total contract value.

8,000,000 x 40.98 = 3.278.400‬

cost                           2,500,000    

income                          778.400‬

2023

we recognize the remaining revenue.

8,000,000 - 2,666,667 - 3,278,400 = 2.054.933‬ revenue

cost 3,800,000

loss   1,745,067‬

If on February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. The amount of revenue and gross profit or loss to be recognized in each of the three years will be:      

Revenue to be recognized            

  • 2018 $2,833,050    
  • 2019 $1,889,550    
  • 2020 $3,777,400

Gross profit (loss) to be recognized

  • 2018 $833,050    
  • 2019 -$610,450        
  • 2020 -$22,600

                                                      2018                 2019                    2020      

Billings during the year             $2,500,000      $2,750,000     $3,250,000

                                                        2018                 2019                    2020      

Costs incurred during the year    $2,000,000     $2,500,000     $3,800,000

Cumulative costs to date              $2,000,000     $4,500,000      $8,300,000

Add estimated costs to complete $4,000,000     $3,600,000              $0      

Estimated total costs                     $6,000,000   $8,100,000       $8,300,000

2020 Billings during the year=$8,000,000-$2,500,000-$2,250,000

2020 Billings during the year=$3,250,000

2019 Cumulative cost to date=$2,500,000+$2,000,000

2019 Cumulative cost to date=$4,500,000

2020 Cumulative cost to date=$4,500,000+$3,800,000

2020 Cumulative cost to date=$8,300,000

Percentage of completion

2018     $2,000,000/$6,000,000×100=33.33%  

2019      $4,500,000/$8,100,000×100=55.56%      

2020     $8,300,000/$8,300,000×100=100%

Contract price of this project                        $8,500,000

($2,500,000+$2,750,000+$3,250,000)

Less cumulative cost to date till 2020          $8,300,000

Contract estimated gross profit (loss)           $200,000  

                                                        2018                 2019                    2020    

Contract value completed            $2,833,050   $4,722,600     $8,500,000

Less revenue recognized              $0                -$2,833,050   -$4,722,600      

Revenue to be recognized            $2,833,050     $1,889,550    $3,777,400

Less cost incurred                          $2,000,000     $2,500,000    $3,800,000

Gross profit (loss) to be recognized $833,050     -$610,450        -$22,600

2018 Contract value completed = ($8,500,000×33.33%=$2,833,050)

2019 Contract value completed = ($8,500,000×55.56%=$4,722,600)

2020 Contract value completed =($8,500,000×100%=$8,500,000)

Learn more here:

https://brainly.com/question/15540744