You work as a coordinator for data entry projects. On one project, the status shows that 15% of the work was completed in 6 days. If the work progresses at the same rate, how many more days will be required to complete the remainder of the project.

Respuesta :

Answer: 36 more days

Step-by-step explanation:

it averages out to 2.5% per day