Consider the following project:
Activity Immediate Predecessor Duration in Weeks
A None 2
B None 3
C A 4
D A and B 4
E C and D 3
Which activities are noncritical?
a) A, C, E
b) A, C
c) B, D, E
d) B, C
e) None of the above