.The Office Furniture Company produces a desk from 2 drawers, 2 legs, and other components. Drawers and legs have the following data, in minutes, and each require a setup
Drawers
Run time
Setup time
Machine 1
4
30
Machine 2
2
10
Machine 3
5
50
Legs
Run time
Setup time
Machine 1
2
20
Machine 2
3
15
Machine 3
4
30
The master production schedule for weeks 1-3 has a quantity of 30 desks. There is a setup for each MPS quantity. What are the capacity requirements for each of the three machines next week?
Machine 1:650 minutes, Machine 2: 500 minutes, Machine 3: 780 minutes each week
Machine 1: 410 minutes, Machine 2: 325 minutes, Machine 3: 620 minutes each week
Machine 1: 500 minutes, Machine 2: 525 minutes, Machine 3: 675 minutes each week
Machine 1: 850 minutes, Machine 2: 390 minutes, Machine 3: 800 minutes each week
Machine 1: 595 minutes, Machine 2: 654 minutes, Machine 3: 777 minutes each week