When performing a forward pass calculation to determine the critical path of a network when multiple paths converge into a successor activity, the value carried forward to the early start of the successor activity is .
The smallest early finish of the successor's immediate predecessors.
The smallest late finish of the successor's immediate predecessors.
The largest late finish of the successor's immediate predecessors.
The largest early finish of the successor's immediate predecessors.